DAS Phase III: Status report

  • Thread starter Thread starter Thakur
  • Start date Start date
  • Replies Replies: Replies 0
  • Views Views: Views 559

Thakur

Banned
Joined
30 Aug 2013
Messages
14,856
Reaction score
8,575
It was in September 2014 when the then Information and Broadcasting Minister Prakash Javadekar extended the deadline for completion of phase III of cable TV digitization. Not only did Javadekar extend the deadline, but also set separate deadlines for phase III and IV, which initially were supposed to be completed in the same time frame.
 
So, while the deadline for phase III was set to be December 2015, phase IV could be completed by December 2016.
 
Notwithstanding these developments, it should be noted that interconnect agreements between multi system operators (MSOs) and last mile owners (LMOs) are not in place for phase I and II cities even now. Moreover, close to 700 MSOs interested in phase III areas have not yet been given the license to operate.
 
With no announcement about the new Telecom Regulatory Authority of India (TRAI) chairman, the huge number of litigations between broadcasters, MSOs and LMOs pending in several High Courts and with the Telecom Disputes Settlement and Arbitration Tribunal (TDSAT), there looms a big question mark on the timely completion of Digital Addressable System (DAS) for phase III.
 
Maharashtra Cable Operators Federation president Arvind Prabhoo says that not more than five per cent of the cable TV homes falling in the phase III universe would have been digitized.
 
“The government will have to step in if they want the deadline to be met. The government needs to incentivize cable operators by coming up with a cable modernization fund, which could be set at Rs 500 per subscriber. This can be recovered by the government in the next two years through GST,” he said.
 
Prabhoo also points out that close to nine crore cable TV households in the phase III areas need to be digitized. “If the government sets incentive of Rs 500 per subscriber, we are looking at a modernization fund of only Rs 4500 crore for the whole ‘Digital India’ campaign. I am sure it is not asking for much,” he added.
 
MSO Hathway Cable & Datacom along with its various subsidiaries has already seeded 50 per cent of its universe. Speaking toIndiantelevision.com on the issues affecting the smooth rollout of digitization in phase III, Hathway MD & CEO Jagdish Kumar Pillai said, “The biggest issue is getting content agreements executed at reasonable costs. The government is doing excellent work in facilitating this process.”
 
The government on its part has been taking steps like holding not just task force meetings, but also consumer outreach programmes to ensure that the deadline for phase III is met. “We should be thankful to the government for taking a pro-active role in organising task force meetings and also meeting with and between stakeholders. Now it is up to the industry to step up and make it happen,” added Pillai.
 
A source in TRAI tells this website that there will be no extension in the deadline for phase III. “The government may help facilitate the process, but there is no question of any more extension,” the source said adding that the consumer today is prepared to pay, and the broadcaster is going all out to publicise its digitised platforms. “So if there is any delay from LCOs or MSOs, the consumer will find other ways of going digital, which could be moving to HITS or DTH platform,” the source said.

http://www.indiantelevision.com/cable-tv/msos/das-phase-iii-status-report-150613
 